Question: A project manager hired 16 men to complete a project in 38 days. However, after 30 days, he realised that only $ \frac{5}{9}th $ of the work is complete. How many more men does he need to hire to complete the project on time? [SBI (PO) 2015]
Options:
A) 48
B) 24
C) 32
D) 16
E) 36
Show Answer
Answer:
Correct Answer: C
Solution:
- [c] Given, $ M _1=16, $ $ D _1=30, $ $ W _1=\frac{5}{9}, $ $ M _2=x, $
$ D _2=8, $ $ W _2=\frac{4}{9} $
Using the formula,
$ \frac{M _1D _1}{W _1}=\frac{M _2D _2}{W _2} $
$ \Rightarrow $ $ \frac{16\times 30}{\frac{5}{9}}=\frac{x\times 8}{\frac{4}{9}} $
$ \Rightarrow $
$ \Rightarrow $
$ \Rightarrow $ $ x=48 $
$ \therefore $ More men needed to hire to complete the project on time $ =48-16=32 $ men