A) 10 days
B) 11 days
C) 9 days
D) 12 days
Correct Answer: D
$ \therefore $ Work done by both in 9 days $ =\frac{9}{2}\times \frac{8}{45}=\frac{4}{5} $ Now, remaining work $ =1-\frac{4}{5}=\frac{1}{5} $ Next day, B will do the work.
$ \therefore $ Time taken by B to complete the work $ =\frac{1}{5}\times 15=3,days $
$ \therefore $ Total time taken to complete the work $ =(9+3),days=12,days $