Quantitative Aptitude Ques 31

Question: A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

Options:

A) 11 days

B) 13 days

C) $ 20\frac{3}{17}days $

D) None of these

Show Answer

Answer:

Correct Answer: B

Solution:

  • Ratio of times taken by A and $ B=100:130=10:13 $ Suppose B takes x days to do the work. Then, $ 10:13::23:x $

$ \Rightarrow $ $ x=( \frac{23\times 13}{10} ) $
$ \Rightarrow $ $ x=\frac{299}{10} $ A’s 1 days work $ =\frac{1}{23}; $ B’s 1 day’s work $ =\frac{10}{299}. $ $ (A+B)’s $ 1 day’s work $ =( \frac{1}{23}+\frac{10}{299} )=\frac{23}{299}=\frac{1}{13} $ So, A and B together can complete the job in 13 days. Alternate Method Let A takes x days to complete the work, then B will take $ x+\frac{30x}{100}=\frac{13x}{10},days $ If they work together, $ (A+B)’s $ 1 day work $ =\frac{1}{x}+\frac{10}{13x}=\frac{23}{13x} $ Here, $ x=23 $ (as A can complete the work alone in 23 days)

$ \Rightarrow $ $ (A+B)’s $ 1day work $ =\frac{23}{13\times 23}=\frac{1}{13} $

$ \therefore $ Together they can complete the work in 13 days.