Quantitative Aptitude Ques 261
Question: A completes a piece of work in 4 days and B completes it in 6 days. If both A and B work together, then the number of days required to complete the same work is
Options:
A) $ 3\frac{4}{5},days $
B) $ 2\frac{3}{5},days $
C) $ 2\frac{2}{5},days $
D) $ 3\frac{2}{5},days $
Show Answer
Answer:
Correct Answer: C
Solution:
- Total number of days required to complete the work
$ =\frac{4\times 6}{4+6}=\frac{24}{10}=\frac{12}{5}=2\frac{2}{5}days $