Question: A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in
Options:
A) 4 days
B) 5 days
C) 6 days
D) 7 days
Show Answer
Answer:
Correct Answer: C
Solution:
- Given,(A + B)’s 1 day’s work $ =\frac{1}{8} $ … (i)
(B + C)‘s1 day’s work $ =\frac{1}{2} $ … (ii)
(C + A)’s 1 day’s work $ =\frac{1}{8} $ … (iii)
On adding Eqs. (i), (ii) and (iii), we get
2 (A + B + C)’s 1 day’s work
$ =\frac{1}{8}+\frac{1}{12}+\frac{1}{8}=\frac{3+2+3}{24}=\frac{8}{24}=\frac{1}{3} $
$ \therefore $ (A + B + C)’s 1 day’s work $ =\frac{1}{6} $
Hence, the work will be completed in 6 days.