Question: Seventy five men are employed to lay down a railway line in 3 months. Due to certain emergency conditions, the work was to be finished in 18 days. How many more men should be employed to complete the work in the desired time?
Options:
A) 300
B) 326
C) 350
D) 375
Show Answer
Answer:
Correct Answer: A
Solution:
- 75 men can lay down railway line in 3 months,
i.e. $ (3\times 30=90\text{days)} $
Now, let x men can lay down railway line in 18 days.
We know that,
$ M _1D _1=M _2D _2 $
(i)
Here, $ M _1=75, $ $ D _1=90 $
$ M _2=x, $ $ D _2=18 $
On putting the values in Eq. (i), we get
$ 75\times 90=x\times 18 $
$ \Rightarrow $ $ x=\frac{75\times 90}{18} $
$ \Rightarrow $ $ x=75\times 5=375men $
$ \therefore $ 375 men can lay down railway line in 18 days.
Now, number of more man required will be
$ =375-75=300men $