Quantitative Aptitude Ques 1333

Question: Working 7 h daily 24 men can complete a piece of work in 27 days. In how many days would 14 men complete the same piece of work working 9 h daily?

Options:

A) 29

B) 39

C) 36

D) 80

Show Answer

Answer:

Correct Answer: C

Solution:

  • Total work done by 24 men in 27 days with 7 h daily $ =24\times 7\times 27 $

$ \therefore $ Required days $ =\frac{24\times 7\times 27}{9\times 14}=36 $