Question: Working 7 h daily 24 men can complete a piece of work in 27 days. In how many days would 14 men complete the same piece of work working 9 h daily?
Options:
A) 29
B) 39
C) 36
D) 80
Show Answer
Answer:
Correct Answer: C
Solution:
- Total work done by 24 men in 27 days with 7 h daily $ =24\times 7\times 27 $
$ \therefore $ Required days $ =\frac{24\times 7\times 27}{9\times 14}=36 $