Question: 12 men and 16 boys can do a piece of work in 5 days while 13 men and 24 boys finish it in 4 days. 5 men and 10 boys will finish it in
Options:
A) 10 days
B) 12 days
C) 9 days
D) 15 days
Show Answer
Answer:
Correct Answer: A
Solution:
- $ (12m+16b) $ can do a work in 5 days.
$ (60m+80b) $ can do a work in 1 day.
$ (13m+24b) $ can do a work in 4 days.
$ (52m+96b) $ can do a work in 1 day.
$ 60m+80b=52m+96b $
$ \Rightarrow $ $ 8m=16b $
$ \Rightarrow $ $ m=2b $
Now, $ 12m+16b=12\times 2+16=40 $ boys can do work in 5 days.
$ \therefore $ $ 5m+10b=[5\times 2+10] $
= 20 boys will take
$ =\frac{40\times 5}{20}=10days $